Construction Change Order Request Form for Word
A change order is the only clean way to change a construction contract after it is signed: it says exactly what changed, why, what it costs, how many days it adds, and who agreed. This form is a finished three-page example for a fictional medical office build-out, with an itemized cost breakdown, the running contract sum from the original amount through every approved change, and completion dates before and after.
- Pages:
- 3
- Works with:
- Word for Microsoft 365, Word 2016 or later, Word for Mac (Word for the web can fill in fields)
- Updated:
What you can do with it
- Project block with requested-by and status dropdowns and contract and change order date pickers
- Description of change, reason dropdown (owner request, design error, unforeseen condition, code, value engineering) and affected drawings
- Itemized cost breakdown with subtotal, overhead and profit and bond, and a contract sum reconciliation
- Schedule impact with completion dates before and after, attachments checklist and three-party approval

What's inside
The document has 3 pages. Each part below is a heading in the file, so you can jump to it from the Navigation Pane (View > Navigation Pane).
| Part | What it covers | What you write |
|---|---|---|
| Project block | Which contract and which change | Project, number, owner, contractor, architect, contract date, CO number and date, requester, status |
| 1. Description of change | What changes and why | Scope text, reason, affected drawings and specifications |
| 2–3. Cost and contract sum | What it costs and the new contract total | Quantities, unit costs, markups; original sum, previous changes, new sum |
| 4. Schedule impact | Days added and new completion | Days, completion before and after, reason |
| 5–6. Attachments and approval | Backup and authority | Quotes, drawings, reports; owner, contractor and architect signatures |
Before you start
- Check the contract’s change clause: who can request changes, the markup allowed on changed work, and how time extensions are claimed.
- Get subcontractor quotes or a takeoff before pricing.
- Have the current contract sum: the original amount plus every approved change order so far.
Step-by-step guide
Fill in the project block
Type the project, parties and change order number, pick the dates, who requested the change and its status.
Describe the change
Say exactly what work is added, removed or changed, pick the reason from the dropdown and list every drawing and specification section affected.
Price it
One row per item with quantity, unit and unit cost. Apply the overhead, profit and bond rates your contract allows, and check every amount adds up.
Update the contract sum
Carry the original sum and the net of previous change orders, add this change and show the new contract sum.
State the time impact
Enter the days added, pick the completion dates before and after, and say why the work affects the critical path.
Attach backup and sign
Tick the attachments, set the status to Pending approval, and collect the owner, contractor and architect signatures. Then set the status to Approved.
Field and control map
Every content control and field in the document, in the order they appear. Gray-boxed fields in Word are the content controls.
| Name | Type | Where | Value in the sample |
|---|---|---|---|
| Change order number | Text | Header | CO-007 |
| Project name header | Text | Header | Elm Street Medical Office Build-Out |
| Project name | Text | Body | Elm Street Medical Office Build-Out |
| Project number | Text | Body | 2026-031 |
| Owner | Text | Body | Elm Street Health Partners |
| Contractor | Text | Body | Keystone Builders, Inc. |
| Architect | Text | Body | Harlow + Fenn Architects |
| Contract date | Date picker | Body | May 4, 2026 |
| Change order number | Text | Body | CO-007 |
| CO date | Date picker | Body | November 2, 2026 |
| Requested by | Dropdown | Body | Owner (Owner / Contractor / Architect / Engineer) |
| CO status | Dropdown | Body | Pending approval (Draft / Pending approval / Approved / Rejected / Void) |
| Change reason | Dropdown | Body | Owner request (Owner request / Design error or omission / Unforeseen site condition / Code or inspector requirement / Value engineering / Allowance adjustment) |
| Days added | Text | Body | 4 |
| Completion before | Date picker | Body | February 19, 2027 |
| Completion after | Date picker | Body | February 23, 2027 |
| Att quote | Checkbox | Body | checked |
| Att drawings | Checkbox | Body | checked |
| Att report | Checkbox | Body | checked |
| Att photos | Checkbox | Body | unchecked |
| Owner signer | Text | Body | Dr. Nina Park, Managing Partner |
| Signed date | Date picker | Body | 3 fields: Click or tap to enter a date. |
| Contractor signer | Text | Body | Ray Collins, Project Manager |
| Architect signer | Text | Body | Leah Harlow, AIA |
{ PAGE } | Field | Footer | 1 |
{ NUMPAGES } | Field | Footer | 3 |
{ SEQ Table \* ARABIC } | Field | Body | 1 |
Every field, control and style, explained
The code in each card is read straight from the .docx file (the XML Word stores, or the field code you see with Alt+F9), so it is exactly what the template contains.
<w:lvl w:ilvl="0">
<w:start w:val="1"/>
<w:numFmt w:val="decimal"/>
<w:pStyle w:val="Heading1"/>
<w:lvlText w:val="%1."/>
<w:lvlJc w:val="left"/>
<w:pPr>
<w:ind w:left="440" w:hanging="440"/>
</w:pPr>
</w:lvl>
<w:lvl w:ilvl="1">
<w:start w:val="1"/>
<w:numFmt w:val="decimal"/>
<w:pStyle w:val="Heading2"/>
<w:lvlText w:val="%1.%2"/>
<w:lvlJc w:val="left"/>
<w:pPr>
<w:ind w:left="660" w:hanging="660"/>
</w:pPr>
</w:lvl>The section numbers (1., 2., 6.1 …) are not typed. A multilevel list is linked to the Heading 1 and Heading 2 styles, so any paragraph you set to Heading 1 gets the next number and the table of contents picks it up.
Piece by piece
<w:pStyle w:val="Heading1"/>- Links list level 1 to the Heading 1 style (level 2 to Heading 2).
<w:lvlText w:val="%1."/>- Level 1 shows its counter and a period: 1., 2., 3.
<w:lvlText w:val="%1.%2"/>- Level 2 shows the parent number, a period and its own counter: 6.1, 6.2.
<w:ind w:left="440" w:hanging="440"/>- Hanging indent so wrapped heading text lines up after the number.
In the sample: 1. Description of change, 1.1 Reason for change, 1.2 Drawings and specifications affected … (8 headings)
How it is used: To add a section, type the heading, then pick Heading 1 (Ctrl+Alt+1) or Heading 2 (Ctrl+Alt+2) on the Home tab. Numbers after it update by themselves.
How to change it: Home > Multilevel List > Define New Multilevel List to change the format (for example "Section 1"). Keep "Link level to style" set to Heading 1 and Heading 2.
Learn this: How to Plan and Structure Long Documents in Word: Outline View and Multilevel Numbering →Page { PAGE } of { NUMPAGES }The footer counts pages with two fields: PAGE is the current page and NUMPAGES is the total. Both recalculate when the document is printed, saved as PDF or scrolled in Print Layout.
Piece by piece
PAGE- The number of the page the field sits on.
NUMPAGES- The total number of pages in the document.
In the sample: Page 1 of 3 on the first page
How it is used: Nothing to do: add or delete pages and the numbers follow.
How to change it: Double-click the footer to edit the text around the fields. Insert > Page Number > Format Page Numbers sets the starting number.
Learn this: How to Set Up Pages in Word: Margins, Breaks, Headers, Footers, and Page Numbers →{ SEQ Table \* ARABIC }Each table caption uses a SEQ field that counts tables in order. Insert a new captioned table in the middle and every later caption renumbers.
Piece by piece
SEQ Table- A counter named "Table". Every SEQ Table field adds 1.
\* ARABIC- Show the counter as 1, 2, 3.
In the sample: 1 caption(s): Table 1
How it is used: Captions are what a "see Table 2" cross-reference points to (References > Cross-reference).
How to change it: References > Insert Caption adds a new one. If numbers look stale, press Ctrl+A then F9 to update all fields.
Learn this: How to Add a Table of Contents, Captions, and Cross-References in Word →<w:sdtPr>
<w:alias w:val="Project name"/>
<w:tag w:val="project_name"/>
<w:text/>
</w:sdtPr>Names, numbers and other details people change every time are plain text content controls. Click one and type: the text replaces the sample, keeps the formatting, and the field still shows its name when selected.
Piece by piece
<w:alias w:val="…"/>- The title shown on the control’s tab when you click it.
<w:tag w:val="…"/>- A machine-readable name, useful for mail merge or code.
<w:text/>- Plain text: one line, one format, so pasted text cannot break the layout.
<w:showingPlcHdr/>- Present when the field shows gray placeholder text instead of a value.
In the sample: Project name = Elm Street Medical Office Build-Out
How it is used: 12 in this template: Change order number, Project name header, Project name, Project number, Owner, Contractor, Architect, Days added, Owner signer, Contractor signer, Architect signer. Use Developer > Design Mode to see every control at once, or the Selection Pane to jump between them.
How to change it: Developer > Properties changes the title, tag and placeholder. To show the Developer tab: File > Options > Customize Ribbon > Developer.
Learn this: How to Create Fillable Forms with Content Controls in Word →<w:sdtPr>
<w:alias w:val="Contract date"/>
<w:tag w:val="contract_date"/>
<w:date w:fullDate="2026-05-04T00:00:00Z">
<w:dateFormat w:val="MMMM d, yyyy"/>
<w:lid w:val="en-US"/>
<w:storeMappedDataAs w:val="dateTime"/>
<w:calendar w:val="gregorian"/>
</w:date>
</w:sdtPr>Dates are date picker content controls: click the arrow to pick from a calendar, or type a date in any format and Word shows it as "November 2, 2026".
Piece by piece
w:fullDate- The stored date, independent of how it is shown.
<w:dateFormat w:val="MMMM d, yyyy"/>- Display format: full month name, day, four-digit year.
<w:lid w:val="en-US"/>- Language used for month names.
<w:storeMappedDataAs w:val="dateTime"/>- Stores a real date value if the control is mapped to data.
In the sample: Contract date = May 4, 2026
How it is used: 7 in this template: Contract date, CO date, Completion before, Completion after, Signed date. Pick the date from the calendar so every date in the document has the same format.
How to change it: Developer > Properties > Display the date like this, for example d MMMM yyyy or yyyy-MM-dd.
Learn this: How to Create Fillable Forms with Content Controls in Word →<w:sdtPr>
<w:alias w:val="Requested by"/>
<w:tag w:val="requested_by"/>
<w:dropDownList>
<w:listItem w:displayText="Owner" w:value="Owner"/>
<w:listItem w:displayText="Contractor" w:value="Contractor"/>
<w:listItem w:displayText="Architect" w:value="Architect"/>
<w:listItem w:displayText="Engineer" w:value="Engineer"/>
</w:dropDownList>
</w:sdtPr>Fields with a fixed set of answers are dropdown list content controls, so everyone uses the same words (useful when you search or count documents later).
Piece by piece
<w:dropDownList>- A list the reader must pick from (no free typing).
<w:listItem w:displayText="…" w:value="…"/>- One choice: the text shown and the value stored.
In the sample: Requested by = Owner (Owner / Contractor / Architect / Engineer)
How it is used: 3 in this template: Requested by, CO status, Change reason. Click the field and choose from the list.
How to change it: Developer > Properties > Add, Modify or Remove choices. Use a Combo Box instead if people need to type their own answer.
Learn this: How to Create Fillable Forms with Content Controls in Word →<w:sdtPr>
<w:alias w:val="Att quote"/>
<w:tag w:val="att_quote"/>
<w14:checkbox>
<w14:checked w14:val="1"/>
<w14:checkedState w14:val="2612" w14:font="MS Gothic"/>
<w14:uncheckedState w14:val="2610" w14:font="MS Gothic"/>
</w14:checkbox>
</w:sdtPr>Checklist boxes are checkbox content controls: click to tick or untick. They print as ☒ and ☐.
Piece by piece
<w14:checked w14:val="…"/>- 1 when ticked, 0 when not.
<w14:checkedState w14:val="2612"/>- Symbol for ticked: U+2612 ☒.
<w14:uncheckedState w14:val="2610"/>- Symbol for unticked: U+2610 ☐.
In the sample: 3 of 4 ticked in the sample
How it is used: 4 in this template: Att quote, Att drawings, Att report, Att photos. Click the box. Checkboxes need Word 2010 or later; very old versions show a static symbol.
How to change it: Developer > Properties > Checked symbol > Change, for example to ✓ (Wingdings 2).
Learn this: How to Create Fillable Forms with Content Controls in Word →<w:trPr>
<w:cantSplit/>
<w:tblHeader/>
</w:trPr>Header rows are marked to repeat at the top of each page when a table breaks, and rows are set not to split across pages, so a long table stays readable when printed.
Piece by piece
<w:tblHeader/>- Repeat this row at the top of each page.
<w:cantSplit/>- Keep each row on one page.
In the sample: 1 of 6 tables repeat their header row
How it is used: Add rows with Tab in the last cell; the header keeps repeating.
How to change it: Click in the header row > Table Layout > Repeat Header Rows. Short tables are also set to keep with the next paragraph so they do not split.
Learn this: How to Build and Format Tables That Read Well in Word →<w:style w:type="paragraph" w:styleId="Guidance">
<w:name w:val="Guidance"/>
<w:basedOn w:val="Normal"/>
<w:pPr>
<w:spacing w:after="100"/>
</w:pPr>
<w:rPr>
<w:i/>
<w:iCs/>
<w:color w:val="6B7280"/>
<w:sz w:val="19"/>
</w:rPr>
</w:style>Instructions for whoever fills in the template use a Guidance style (gray italics). Delete them before you send the document; with a style, Find and Replace can remove them all at once.
Piece by piece
<w:i/>- Italic.
<w:color w:val="6B7280"/>- Gray text.
In the sample: One note under the title block.
How it is used: Home > Replace > More > Format > Style > Guidance finds every note.
How to change it: Right-click Guidance in the Styles gallery > Modify.
Learn this: How to Use Styles and the Navigation Pane in Word →Tips and limits
- Price changes before the work starts whenever you can. Work done first and priced later is where most disputes start.
- A change with no cost still needs a change order if it changes scope or time.
- Keep a change order log: the contract sum line on each new change order should match it.
- Markups for overhead, profit and bond are usually set in the contract; use those rates, not new ones.
- Industry forms (for example AIA G701) may be required by your contract. This template is not legal advice.